Possession was promised for December 2023. It is now 2026, the tower is at the eleventh floor of eighteen, and the builder’s office has just sent a demand for the next instalment along with a letter explaining that the delay was caused by circumstances beyond anybody’s control.
Meanwhile the buyer is paying rent and a home loan instalment at the same time, which is the squeeze that makes people accept whatever the builder offers. There is a forum designed precisely for this situation, it is cheap, and it does not require a lawyer. What it requires is that you stop negotiating by telephone and start creating a record.
The real estate regulation law is implemented by a separate authority in each state, with its own portal, fee, forms and timelines, and the rules change. Check your own state authority’s current procedure, and take advice on anything specific to your agreement.
What your agreement already entitles you to

Most buyers have never read the clause that matters, and it is usually in their favour.
A committed possession date. The agreement for sale states one, together with any grace period. That date is the benchmark against which everything else is measured, and a builder’s later letters revising it do not change it unless you agreed in writing.
Interest on the delay, payable by the builder. Where possession is not given by the committed date, the law provides for interest payable to the allottee for the period of delay, at a rate the rules prescribe — and importantly, at the same rate the builder would have charged you for a late payment. That symmetry is deliberate.
A right to withdraw. On a delay you may choose: continue with the project and claim interest for every month of delay until possession, or withdraw and claim a refund of what you paid with interest and, where applicable, compensation. The choice belongs to you. Builders routinely tell buyers that exiting means forfeiting a deposit; on a builder’s own delay, that is not how the law reads.
Payments linked to construction stages. Your instalments are tied to defined stages of construction, not to the builder’s cash requirements. A demand for money for a stage that has not been reached is one you can question in writing — and should, because paying it weakens your position later.
Defect liability after possession. Structural defects and poor workmanship reported within the period the law allows are the builder’s responsibility to rectify.
Before you file

- Pull the project’s page from your state authority’s website. Every registered project has one, showing the registration number, the declared completion date, the approvals and the quarterly progress updates the builder itself filed. Download and date-stamp these. A builder telling you the project is on schedule while its own quarterly filing says otherwise is a useful thing to have in writing.
- Assemble the file. The allotment letter, the registered agreement for sale, every payment receipt with dates and amounts, every demand letter, your bank statements showing the payments, the loan sanction letter, and every piece of correspondence including the ones you sent on the builder’s own portal.
- Build a one-page chronology. Committed date, each payment with its date and amount, each demand, each promise of a revised date, and today. This single page does more work than any amount of argument.
- Write to the builder. A short letter, by email and by registered post, stating the committed date, the current status, and asking for a firm possession date in writing. Keep the delivery proof. You are not expecting a useful reply; you are establishing that you asked.
- Decide what you want before you file — interest and possession, or refund with interest and exit — because the complaint has to ask for something specific.
- Do not sign anything the builder offers in the meantime. Revised agreements, waivers, “settlement” letters and no-objection documents presented at the site office frequently extinguish exactly the claim you are about to make. Take them home and have them read.
Filing, and what it costs
Complaints are filed with the state authority, generally through an online portal, on a prescribed form, with a modest fee. You may appear yourself; engaging an advocate is optional and for a straightforward delay claim often unnecessary.
The complaint should contain the project registration number, your allotment details, the chronology, the specific relief you want expressed in numbers, and the documents attached. Hearings follow, often with both parties appearing, and the authority passes an order.
Two things to understand about the outcome:
An order is not money in your account. If the builder does not comply, the order has to be enforced, which is a separate application and takes further time. This is the stage at which buyers give up, and it is worth knowing in advance so you plan for it.
An appeal lies to the appellate tribunal within the stated period, and either side may use it. A builder appealing to delay matters further is common, which is another reason to file early rather than after four more years of waiting.
File together
The most underused tool in this entire area is the association of allottees.
Buyers in a stalled project are generally in an identical position, holding near-identical agreements, with the identical grievance. Filing together — or forming an association and acting through it — means the documents are assembled once, the cost is shared, the hearings are attended by whoever is available, and the authority is dealing with a project-wide failure rather than one person’s complaint.
It also removes the builder’s most effective tactic, which is to settle quietly with the loudest complainant on slightly better terms and let the rest continue waiting.
Practically: find the project’s buyer group, verify who actually holds allotments, agree on what the group is asking for, and keep the group’s records in one shared place.
The loan, while you wait
The hardest part of a delay is financial rather than legal, and it deserves saying plainly.
- Keep paying the loan instalments. Stopping damages your credit record, which is a separate and lasting injury, and it does not pressure the builder at all.
- Ask the lender about the disbursement. Where the loan is disbursed in stages against construction, tell the lender in writing that the stage has not been reached, so further disbursement — and the interest on it — does not run ahead of the construction.
- Know the tax position. The deduction available on home loan interest for a self-occupied property depends on the property being completed within a period from the loan being taken, and a long delay can affect what you may claim. Confirm the current rules for your situation with a tax adviser before filing your return.
- Claim the delay interest in your complaint, since it is intended to offset exactly this — the rent and the instalment you are paying together.
- Do not fund further stages out of turn in the hope of accelerating things. Money paid ahead of the construction stage is money you have to recover later.
Frequently asked questions
What am I entitled to if possession is late?
Either to continue and claim interest from the builder for every month of delay at the rate the rules prescribe, or to withdraw and claim a refund of what you paid with interest. The choice is yours, not the builder’s.
The builder says I will forfeit my deposit if I exit. Is that right?
Not where the builder is the one in delay. That forfeiture argument applies to a buyer walking away without cause, and it is routinely quoted at buyers in stalled projects. Get the clause read before accepting it.
Do I need a lawyer to file?
No. Complaints are filed on a prescribed form through the state authority’s portal for a modest fee, and you may appear yourself. For a straightforward delay claim an advocate is optional.
What is the single most useful document?
The project’s own page on the state authority’s website, with the declared completion date and the quarterly progress updates the builder itself filed. It frequently contradicts what the site office is telling you.
Should I stop paying my home loan instalments while the project is stalled?
No. It damages your credit record lastingly and puts no pressure on the builder. Instead, write to the lender about pausing further stage-wise disbursement where the construction stage has not been reached.
Is it better to file alone or with other buyers?
Together. The documents are assembled once, the cost and the hearings are shared, and the authority deals with a project-wide failure rather than one complaint — which also removes the builder’s tactic of settling quietly with the loudest buyer.
In short
Your agreement states a possession date, and missing it entitles you either to interest for every month of delay or to a refund with interest if you choose to exit — your choice, whatever the site office says about forfeited deposits. Instalments are tied to construction stages too, so a demand for a stage not reached is one to question in writing rather than pay.
Before filing, download the project’s own page from your state authority — the declared completion date and the builder’s own quarterly progress filings are often the strongest document you will have. Assemble the agreement, every receipt and every demand into a one-page dated chronology, write to the builder asking for a firm date by email and registered post, decide whether you want possession with interest or a refund, and sign nothing the site office puts in front of you without having it read.
Then file online with the state authority, which costs little and needs no lawyer, and expect to enforce the order as a separate step — that is where people give up. File together with the other buyers if you can, because it shares the work and removes the builder’s favourite tactic. And through all of it, keep paying your loan instalments while asking the lender to hold back disbursement for stages the builder has not reached.